Projects Fiscal Year 2018-2019

Project Quarterly Updates

Bike and Pedestrian

Project Status Contact
Dry Creek Trail Maintenance Fact Sheet Design is 10% complete, construction Summer 2019 Michael Sacuskie

Local Streets and Roads

Projects Status Contact
Claus Road Pavement Rehabilitation Fact Sheet Design is 95% complete, construction Summer of 2019 Michael Sacuskie
Downtown Master Plan Fact Sheet The City issued an RFP for consultant assistance, with a deadline for submittal of proposals of December 14, 2018.  Eleven proposals were received, which are currently undergoing evaluation. Steve Mitchell
Wylie, Floyd, and Carver Street Improvements Fact Sheet Design is 95% complete, construction Summer of 2019 Michael Sacuskie
Village One Slurry Seal 2019 Fact Sheet Design is 40% complete, construction Summer 2019 Michael Sacuskie

Traffic Management

Projects Status Contact
Installation of Rectangular Flashing Beacon Fact Sheet Design 70% complete, estimated bid date May 2019 James Ashby
Fiber Drop into Traffic Signal Cabinet Fact Sheet No action has occurred. Mark Murphy
Replace 35 Obsolete Traffic Controllers Fact Sheet Request for purchase has been approved and with finance to secure quotes to finalize PO, Scott Collins
Traffic Signal Analysis Study System Wide Fact Sheet Selected Iteris as prime consultant. Going to council January 22 to award contract. Scott Collins
Improve Traffic Flow and Safety @ Orville Wright Elementary Fact Sheet Design is 10% complete, construction Summer 2019 Michael Sacuskie