Lakewood Neighborhood Street Improvement Project design is complete. Anticipate awarding construction contract August 8, 2018 and starting construction in October 2018. Michael Sacuskie
Standiford Pavement Rehabilitation Design is complete. Construction contract awarded to DSS Company dba Knife River Construction on June 26, 2018. Construction anticipated to begin in Sept. 2018. Phillip Soares
Carpenter Road Street Improvements Project is under construction. Construction contracted awarded to DSS dba Knife River Construction on May 22, 2018. Contractor currently working on Carpenter Road between Maze Blvd. and Chicago Ave. Chuck Covolo
Wylie Dr., Floyd Ave.,  and Carver Ave. Street Improvements (Collector Streets) Project design started, 2% complete. Michael Sacuskie